Are You Prepared to "Go Live" With Your Order Management System?

   

Having spent a considerable investment in new software whether it is an order management system ororder management system any system for that matter, the last thing you want to have is a failed implementation.

Unfortunately, flawed system "go live" executions happen all too often. You might wonder how this is possible, after dozens of people have worked for months on an implementation. I think it’s because many companies have not built a readiness assessment for "go live" into their project plans.

READ: 13 Information Technology Cost Reduction & Productivity Improvement Ideas

It’s one thing to be running behind on programming modifications, testing and implementing your systems project. It’s another to unknowingly commit the company to "go live" without management review, risk assessment and agreement and signoff that everything is ready. This isn’t a daylong meeting before "go live", but a built-in process that everyone works towards and knows in advance in terms of plans and criteria for readiness.

The following 10 points should be part of your readiness assessment before management gives its blessing to convert and "go live":

1. Modification process: All testing of modifications need to be done first by IT and then by department management.

2. Testing: Complete end-to-end testing and conference room pilot testing from origination of orders, returns, receipts and shipping through to systems processes. This includes inbound product flow processes and outbound shipping functions. Be sure to process live data through to accounting and management reporting systems.

3. File conversion: Have the necessary files been successfully converted on a test basis and visually spot checked to the files on the current order management system. Then on a test basis convert 10% of the file and calculate how long the actual conversion of all files will take. With SQL systems in large multichannel environments this may take days to convert customer files. How does this affect your plans?

4. More testing: Do volume testing with website and call center phone orders to get a feel for how the order management system system will respond when processing actual transaction volumes.

5. Check the interfaces: Have you tested all the interfaces with vendors, ASN and EDI services, marketing services, credit processors, etc.?

6. Training: Have all the employees in various departments been trained on the new order management system? Are new standard operating procedures (SOPs) in place?

7. IT readiness: Is IT ready to support the company with knowledge of the daily processes, and is all equipment installed in IT and user departments?

8. Who does what: Have agreement on the conversion process and everyone’s "go live" responsibilities.

9. OK from the top: Senior management and department management should sign off only after they’ve reviewed their respective processes and testing results and agree that all critical processes are ready.

READ: How to Improve Your New Systems Selection and Implementation Process

10. Allow critical feedback from the rank and file: Most importantly, create an open communication environment where your employees are empowered and have the courage to say, “No, we’re not ready.” Allow time in your implementation plan to assess your readiness and plan on conducting it within 30 days prior to the scheduled "go live" date.

For sure, there is intense pressure when you miss a "go live" date, as this means incurring additional project costs and taxing limited resources. But the situation becomes much worse when the switch is flipped before you’re ready, in the process, risking the company’s profitability, reputation and customer relationships.